SlideShare a Scribd company logo
1
TESTING OF CIRCUIT BREAKERS
Presented by,
KABILESH. K
(15BEE023)
CONTENTS
 Circuit Breaker
 Types of circuit breaker
 Tests of circuit breaker
 Dielectric and impulse tests
 Thermal tests
 Mechanical tests
 Short circuit tests
2
CIRCUIT BREAKER
 An electromechanical switch that breaks the circuit under fault
condition.
 Unlike a fuse, which operates once and then must be replaced, a
circuit breaker can be reset to resume normal operation.
 To detect a fault condition, and immediately discontinue the
electrical flow.
3
4
TYPES OF CIRCUIT BREAKER
AIR BLAST CB
VACCUM CB
SF6 CB
OIL CB
NEED FOR TESTING
 During short circuit fault or any other types of
electrical fault these equipment suffer a high stress of
fault current which may damage the equipment and
networks.
 For saving these equipments and the power networks,
circuit breakers are used, thereby disconnecting the
circuit.
 Hence, the testing of the circuit breakers are essential.
5
TEST OF CIRCUIT
BREAKERS
Dielectric tests
Impulse tests
Mechanical tests
Thermal tests (Temperature rise tests)
Short Circuit tests
6
DIELECTRIC AND
IMPULSE TESTS
 Dielectric tests:
 Consists of over voltage withstand tests of power frequency,
lightning and switching impulse voltages
 Tested for internal & external insulation with CB in both the open
& closed position.
 Voltage in Open position >15% of that of closed position.
 During test, CB is mounted on insulators above ground to avoid
ground flash over.
 Impulse tests:
 The test is done with switching over voltage.
 To asses their performance under over voltages due to switching
operation.
7
THERMAL TEST
To check the thermal behaviour of the breakers
Rated current through all three phases of the switchgear is
passed continuously for a period long enough to achieve steady
state conditions
Temperature rise must not exceed 40°C when the rated normal
current is less than 800 amps and 50°C if it is 800 amps and
above
Contact resistances between the isolating contacts and
between the moving and fixed contacts is important. These
points are generally the main sources of excessive heat
generation.
8
MECHANICAL TESTS
To ensure the open and closing with out mechanical
failure.
It requires 500(some times 20,000) operations without
failure and with no adjustment of the mechanism.
A resulting change in the material or dimensions of a
particular component may considerably improve the life
and efficiency of the mechanism.
9
SHORT CIRCUIT TESTS
 To check the ability to safely interrupt the fault
currents.
 To determine the breaking capacities at different load
currents
 Methods of conducting short circuit tests,
Direct tests
Using the power utility system as the source.
Using a short circuit generator as the source.
Synthetic Tests
10
DIRECT TESTS
USING THE POWER UTILITY SYSTEM AS THE
SOURCE
 To check the ability to break in normal load conditions or
short circuit conditions in the network itself.
 Done during limited energy consumption.
11
PROS AND CONS OF DIRECT TEST
USING POWER UTILITY SYSTEMS
 Advantages:
1. Tested under actual conditions in a network
2. Special cases (like very short line faults etc.,) can be tested
3. Thermal & dynamic effects of short circuit currents and
applications of safety devices can be studied
 Disadvantages:
1. Can be tested only in rated voltage and capacity of the network
2. Test is only at light load conditions
3. Inconvenience and expensive installation of control and
measuring equipment is required in the field.
12
SHORT CIRCUIT TEST IN
LABORATORIES
 To test the CBs at different voltages & different SC currents.
 The setup consists of,
 A SC generator
 Master CB
 Resistors
 Reactors and
 Measuring devices
 The make switch initiates the circuit short circuit & master breaker
isolates the test device from the source at the end of predetermined
time.
 If the test device failed to operate, master CB can be tripped.
13
Back up
breaker
Short Circuit
Testing Gen
Reactor
Test device
CT
Making
Switch
Circuit
Capacitance
G
SYNTYHETIC TESTS
 Heavy current at low voltage is applied
 Recovery voltage is simulated by high voltage, small current source
 Procedure:
When auxiliary breaker 3 and test circuit breaker T are closed,
making switch 4 and master breaker 1 is closed. Hence, Current
flows through test CB.
At time t0, the test CB begins to operate.
14
1 2 3 4 5 6
Vc Cc C0 Cv
IvIc
T
SYNTHETIC TEST (Contd.,)
 At time t1, just before zero of the gen current, the trigger gap 6 closes
and high frequency current from capacitance Cv flows through the arc
of the gap
 At time t2, gen current is zero. Master CB 1 is opened
 The current from Cv will flow through test CB and full voltage will be
available
 At the instant of breaking, the source is disconnected as the high
voltage is supplied by auxiliary CB 4.
15
1 2 3 4 5 6
Vc Cc C0 Cv
IvIc
T
16
Ad

More Related Content

What's hot (20)

Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
Md Irshad Ahmad
 
Static relay
Static relayStatic relay
Static relay
jawaharramaya
 
**Lightning Arrester Presentation**
**Lightning Arrester Presentation****Lightning Arrester Presentation**
**Lightning Arrester Presentation**
SKPAMB
 
HV testing of insulator
HV testing of insulatorHV testing of insulator
HV testing of insulator
Jawad Ali
 
Capacitor bank and improvement of power factor
Capacitor bank and improvement of power factorCapacitor bank and improvement of power factor
Capacitor bank and improvement of power factor
Ahshan Kabir
 
Relays
RelaysRelays
Relays
Ameen San
 
INSULATORS AND ITS TYPES
INSULATORS AND ITS TYPESINSULATORS AND ITS TYPES
INSULATORS AND ITS TYPES
Raviteja Damerla
 
Tcsc ppt
Tcsc pptTcsc ppt
Tcsc ppt
Prabhu R
 
Faults on Power System
Faults on Power SystemFaults on Power System
Faults on Power System
Vinod Srivastava
 
Directional over current relay
Directional over current relayDirectional over current relay
Directional over current relay
CS V
 
Impulse testing of transformer
Impulse testing of transformerImpulse testing of transformer
Impulse testing of transformer
Preet_patel
 
Electrical bus bar and its types
Electrical bus bar and its typesElectrical bus bar and its types
Electrical bus bar and its types
Jay Ranvir
 
Protective relay
Protective relay Protective relay
Protective relay
Uday Wankar
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
moiz89
 
Protection of transformer
Protection of transformerProtection of transformer
Protection of transformer
Sumeet Ratnawat
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
Novia Putri
 
Electrical Power substation
Electrical Power substationElectrical Power substation
Electrical Power substation
Emran Ali
 
Major electrical equipment in power plants
Major electrical equipment in power plantsMajor electrical equipment in power plants
Major electrical equipment in power plants
Fateh Singh
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
anuphowlader1
 
Tests on insulators
Tests on insulatorsTests on insulators
Tests on insulators
vhasmukh96
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
Md Irshad Ahmad
 
**Lightning Arrester Presentation**
**Lightning Arrester Presentation****Lightning Arrester Presentation**
**Lightning Arrester Presentation**
SKPAMB
 
HV testing of insulator
HV testing of insulatorHV testing of insulator
HV testing of insulator
Jawad Ali
 
Capacitor bank and improvement of power factor
Capacitor bank and improvement of power factorCapacitor bank and improvement of power factor
Capacitor bank and improvement of power factor
Ahshan Kabir
 
Directional over current relay
Directional over current relayDirectional over current relay
Directional over current relay
CS V
 
Impulse testing of transformer
Impulse testing of transformerImpulse testing of transformer
Impulse testing of transformer
Preet_patel
 
Electrical bus bar and its types
Electrical bus bar and its typesElectrical bus bar and its types
Electrical bus bar and its types
Jay Ranvir
 
Protective relay
Protective relay Protective relay
Protective relay
Uday Wankar
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
moiz89
 
Protection of transformer
Protection of transformerProtection of transformer
Protection of transformer
Sumeet Ratnawat
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
Novia Putri
 
Electrical Power substation
Electrical Power substationElectrical Power substation
Electrical Power substation
Emran Ali
 
Major electrical equipment in power plants
Major electrical equipment in power plantsMajor electrical equipment in power plants
Major electrical equipment in power plants
Fateh Singh
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
anuphowlader1
 
Tests on insulators
Tests on insulatorsTests on insulators
Tests on insulators
vhasmukh96
 

Similar to Testing of circuit breakers (20)

Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
Nihal Shiroya
 
Testing of cb
Testing of cbTesting of cb
Testing of cb
SANKET AHER
 
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKERDIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
Ritesh Kumawat
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
johny renoald
 
Vcb ppt.
Vcb ppt.Vcb ppt.
Vcb ppt.
Er Ramgarhia
 
switchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxswitchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptx
DrNiveditaSingh3
 
16950
1695016950
16950
stider007
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
Nadir Baloch
 
Presentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxPresentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptx
RAJKIRANR3
 
Meduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptxMeduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptx
MAHMOUDMOHAMED431205
 
Time current curves
Time current curvesTime current curves
Time current curves
Rabah Zaimeddine
 
Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptx
Satish Pydimarla
 
LV switchgear FINAL.pptx
LV switchgear FINAL.pptxLV switchgear FINAL.pptx
LV switchgear FINAL.pptx
RanjanKumar17478
 
Ellis Patents Cable Cleats Guide - Black Book
Ellis Patents Cable Cleats Guide - Black BookEllis Patents Cable Cleats Guide - Black Book
Ellis Patents Cable Cleats Guide - Black Book
Thorne & Derrick International
 
Meduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptxMeduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptx
MAHMOUDMOHAMED431205
 
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTSCIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
DigantaSinha1
 
Ratio Burden Admittance Testing
Ratio Burden Admittance TestingRatio Burden Admittance Testing
Ratio Burden Admittance Testing
TESCO - The Eastern Specialty Company
 
Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020
nacetwincities
 
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
Rahul Akinapelli
 
Switchgears and its basics in power plant.pptx
Switchgears and its basics in power plant.pptxSwitchgears and its basics in power plant.pptx
Switchgears and its basics in power plant.pptx
magicrahul
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
Nihal Shiroya
 
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKERDIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
Ritesh Kumawat
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
johny renoald
 
switchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxswitchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptx
DrNiveditaSingh3
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
Nadir Baloch
 
Presentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxPresentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptx
RAJKIRANR3
 
Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptx
Satish Pydimarla
 
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTSCIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
DigantaSinha1
 
Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020Rectifier Operations & Maintenance - Don Olson - 2.4.2020
Rectifier Operations & Maintenance - Don Olson - 2.4.2020
nacetwincities
 
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
Rahul Akinapelli
 
Switchgears and its basics in power plant.pptx
Switchgears and its basics in power plant.pptxSwitchgears and its basics in power plant.pptx
Switchgears and its basics in power plant.pptx
magicrahul
 
Ad

Recently uploaded (20)

acid base ppt and their specific application in food
acid base ppt and their specific application in foodacid base ppt and their specific application in food
acid base ppt and their specific application in food
Fatehatun Noor
 
hypermedia_system_revisit_roy_fielding .
hypermedia_system_revisit_roy_fielding .hypermedia_system_revisit_roy_fielding .
hypermedia_system_revisit_roy_fielding .
NABLAS株式会社
 
Machine foundation notes for civil engineering students
Machine foundation notes for civil engineering studentsMachine foundation notes for civil engineering students
Machine foundation notes for civil engineering students
DYPCET
 
Construction Materials (Paints) in Civil Engineering
Construction Materials (Paints) in Civil EngineeringConstruction Materials (Paints) in Civil Engineering
Construction Materials (Paints) in Civil Engineering
Lavish Kashyap
 
ML_Unit_VI_DEEP LEARNING_Introduction to ANN.pdf
ML_Unit_VI_DEEP LEARNING_Introduction to ANN.pdfML_Unit_VI_DEEP LEARNING_Introduction to ANN.pdf
ML_Unit_VI_DEEP LEARNING_Introduction to ANN.pdf
rameshwarchintamani
 
Agents chapter of Artificial intelligence
Agents chapter of Artificial intelligenceAgents chapter of Artificial intelligence
Agents chapter of Artificial intelligence
DebdeepMukherjee9
 
Slide share PPT of NOx control technologies.pptx
Slide share PPT of  NOx control technologies.pptxSlide share PPT of  NOx control technologies.pptx
Slide share PPT of NOx control technologies.pptx
vvsasane
 
Slide share PPT of SOx control technologies.pptx
Slide share PPT of SOx control technologies.pptxSlide share PPT of SOx control technologies.pptx
Slide share PPT of SOx control technologies.pptx
vvsasane
 
Personal Protective Efsgfgsffquipment.ppt
Personal Protective Efsgfgsffquipment.pptPersonal Protective Efsgfgsffquipment.ppt
Personal Protective Efsgfgsffquipment.ppt
ganjangbegu579
 
Transport modelling at SBB, presentation at EPFL in 2025
Transport modelling at SBB, presentation at EPFL in 2025Transport modelling at SBB, presentation at EPFL in 2025
Transport modelling at SBB, presentation at EPFL in 2025
Antonin Danalet
 
Working with USDOT UTCs: From Conception to Implementation
Working with USDOT UTCs: From Conception to ImplementationWorking with USDOT UTCs: From Conception to Implementation
Working with USDOT UTCs: From Conception to Implementation
Alabama Transportation Assistance Program
 
PPT on Sattelite satellite & Radar(1).pptx
PPT on Sattelite satellite & Radar(1).pptxPPT on Sattelite satellite & Radar(1).pptx
PPT on Sattelite satellite & Radar(1).pptx
navneet19791
 
Environment .................................
Environment .................................Environment .................................
Environment .................................
shadyozq9
 
David Boutry - Specializes In AWS, Microservices And Python
David Boutry - Specializes In AWS, Microservices And PythonDavid Boutry - Specializes In AWS, Microservices And Python
David Boutry - Specializes In AWS, Microservices And Python
David Boutry
 
Physical and Physic-Chemical Based Optimization Methods: A Review
Physical and Physic-Chemical Based Optimization Methods: A ReviewPhysical and Physic-Chemical Based Optimization Methods: A Review
Physical and Physic-Chemical Based Optimization Methods: A Review
Journal of Soft Computing in Civil Engineering
 
Design of Variable Depth Single-Span Post.pdf
Design of Variable Depth Single-Span Post.pdfDesign of Variable Depth Single-Span Post.pdf
Design of Variable Depth Single-Span Post.pdf
Kamel Farid
 
ATAL 6 Days Online FDP Scheme Document 2025-26.pdf
ATAL 6 Days Online FDP Scheme Document 2025-26.pdfATAL 6 Days Online FDP Scheme Document 2025-26.pdf
ATAL 6 Days Online FDP Scheme Document 2025-26.pdf
ssuserda39791
 
Artificial intelligence and machine learning.pptx
Artificial intelligence and machine learning.pptxArtificial intelligence and machine learning.pptx
Artificial intelligence and machine learning.pptx
rakshanatarajan005
 
01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf
01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf
01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf
PawachMetharattanara
 
Construction-Chemicals-For-Waterproofing.ppt
Construction-Chemicals-For-Waterproofing.pptConstruction-Chemicals-For-Waterproofing.ppt
Construction-Chemicals-For-Waterproofing.ppt
ssuser2ffcbc
 
acid base ppt and their specific application in food
acid base ppt and their specific application in foodacid base ppt and their specific application in food
acid base ppt and their specific application in food
Fatehatun Noor
 
hypermedia_system_revisit_roy_fielding .
hypermedia_system_revisit_roy_fielding .hypermedia_system_revisit_roy_fielding .
hypermedia_system_revisit_roy_fielding .
NABLAS株式会社
 
Machine foundation notes for civil engineering students
Machine foundation notes for civil engineering studentsMachine foundation notes for civil engineering students
Machine foundation notes for civil engineering students
DYPCET
 
Construction Materials (Paints) in Civil Engineering
Construction Materials (Paints) in Civil EngineeringConstruction Materials (Paints) in Civil Engineering
Construction Materials (Paints) in Civil Engineering
Lavish Kashyap
 
ML_Unit_VI_DEEP LEARNING_Introduction to ANN.pdf
ML_Unit_VI_DEEP LEARNING_Introduction to ANN.pdfML_Unit_VI_DEEP LEARNING_Introduction to ANN.pdf
ML_Unit_VI_DEEP LEARNING_Introduction to ANN.pdf
rameshwarchintamani
 
Agents chapter of Artificial intelligence
Agents chapter of Artificial intelligenceAgents chapter of Artificial intelligence
Agents chapter of Artificial intelligence
DebdeepMukherjee9
 
Slide share PPT of NOx control technologies.pptx
Slide share PPT of  NOx control technologies.pptxSlide share PPT of  NOx control technologies.pptx
Slide share PPT of NOx control technologies.pptx
vvsasane
 
Slide share PPT of SOx control technologies.pptx
Slide share PPT of SOx control technologies.pptxSlide share PPT of SOx control technologies.pptx
Slide share PPT of SOx control technologies.pptx
vvsasane
 
Personal Protective Efsgfgsffquipment.ppt
Personal Protective Efsgfgsffquipment.pptPersonal Protective Efsgfgsffquipment.ppt
Personal Protective Efsgfgsffquipment.ppt
ganjangbegu579
 
Transport modelling at SBB, presentation at EPFL in 2025
Transport modelling at SBB, presentation at EPFL in 2025Transport modelling at SBB, presentation at EPFL in 2025
Transport modelling at SBB, presentation at EPFL in 2025
Antonin Danalet
 
PPT on Sattelite satellite & Radar(1).pptx
PPT on Sattelite satellite & Radar(1).pptxPPT on Sattelite satellite & Radar(1).pptx
PPT on Sattelite satellite & Radar(1).pptx
navneet19791
 
Environment .................................
Environment .................................Environment .................................
Environment .................................
shadyozq9
 
David Boutry - Specializes In AWS, Microservices And Python
David Boutry - Specializes In AWS, Microservices And PythonDavid Boutry - Specializes In AWS, Microservices And Python
David Boutry - Specializes In AWS, Microservices And Python
David Boutry
 
Design of Variable Depth Single-Span Post.pdf
Design of Variable Depth Single-Span Post.pdfDesign of Variable Depth Single-Span Post.pdf
Design of Variable Depth Single-Span Post.pdf
Kamel Farid
 
ATAL 6 Days Online FDP Scheme Document 2025-26.pdf
ATAL 6 Days Online FDP Scheme Document 2025-26.pdfATAL 6 Days Online FDP Scheme Document 2025-26.pdf
ATAL 6 Days Online FDP Scheme Document 2025-26.pdf
ssuserda39791
 
Artificial intelligence and machine learning.pptx
Artificial intelligence and machine learning.pptxArtificial intelligence and machine learning.pptx
Artificial intelligence and machine learning.pptx
rakshanatarajan005
 
01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf
01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf
01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf
PawachMetharattanara
 
Construction-Chemicals-For-Waterproofing.ppt
Construction-Chemicals-For-Waterproofing.pptConstruction-Chemicals-For-Waterproofing.ppt
Construction-Chemicals-For-Waterproofing.ppt
ssuser2ffcbc
 
Ad

Testing of circuit breakers

  • 1. 1 TESTING OF CIRCUIT BREAKERS Presented by, KABILESH. K (15BEE023)
  • 2. CONTENTS  Circuit Breaker  Types of circuit breaker  Tests of circuit breaker  Dielectric and impulse tests  Thermal tests  Mechanical tests  Short circuit tests 2
  • 3. CIRCUIT BREAKER  An electromechanical switch that breaks the circuit under fault condition.  Unlike a fuse, which operates once and then must be replaced, a circuit breaker can be reset to resume normal operation.  To detect a fault condition, and immediately discontinue the electrical flow. 3
  • 4. 4 TYPES OF CIRCUIT BREAKER AIR BLAST CB VACCUM CB SF6 CB OIL CB
  • 5. NEED FOR TESTING  During short circuit fault or any other types of electrical fault these equipment suffer a high stress of fault current which may damage the equipment and networks.  For saving these equipments and the power networks, circuit breakers are used, thereby disconnecting the circuit.  Hence, the testing of the circuit breakers are essential. 5
  • 6. TEST OF CIRCUIT BREAKERS Dielectric tests Impulse tests Mechanical tests Thermal tests (Temperature rise tests) Short Circuit tests 6
  • 7. DIELECTRIC AND IMPULSE TESTS  Dielectric tests:  Consists of over voltage withstand tests of power frequency, lightning and switching impulse voltages  Tested for internal & external insulation with CB in both the open & closed position.  Voltage in Open position >15% of that of closed position.  During test, CB is mounted on insulators above ground to avoid ground flash over.  Impulse tests:  The test is done with switching over voltage.  To asses their performance under over voltages due to switching operation. 7
  • 8. THERMAL TEST To check the thermal behaviour of the breakers Rated current through all three phases of the switchgear is passed continuously for a period long enough to achieve steady state conditions Temperature rise must not exceed 40°C when the rated normal current is less than 800 amps and 50°C if it is 800 amps and above Contact resistances between the isolating contacts and between the moving and fixed contacts is important. These points are generally the main sources of excessive heat generation. 8
  • 9. MECHANICAL TESTS To ensure the open and closing with out mechanical failure. It requires 500(some times 20,000) operations without failure and with no adjustment of the mechanism. A resulting change in the material or dimensions of a particular component may considerably improve the life and efficiency of the mechanism. 9
  • 10. SHORT CIRCUIT TESTS  To check the ability to safely interrupt the fault currents.  To determine the breaking capacities at different load currents  Methods of conducting short circuit tests, Direct tests Using the power utility system as the source. Using a short circuit generator as the source. Synthetic Tests 10
  • 11. DIRECT TESTS USING THE POWER UTILITY SYSTEM AS THE SOURCE  To check the ability to break in normal load conditions or short circuit conditions in the network itself.  Done during limited energy consumption. 11
  • 12. PROS AND CONS OF DIRECT TEST USING POWER UTILITY SYSTEMS  Advantages: 1. Tested under actual conditions in a network 2. Special cases (like very short line faults etc.,) can be tested 3. Thermal & dynamic effects of short circuit currents and applications of safety devices can be studied  Disadvantages: 1. Can be tested only in rated voltage and capacity of the network 2. Test is only at light load conditions 3. Inconvenience and expensive installation of control and measuring equipment is required in the field. 12
  • 13. SHORT CIRCUIT TEST IN LABORATORIES  To test the CBs at different voltages & different SC currents.  The setup consists of,  A SC generator  Master CB  Resistors  Reactors and  Measuring devices  The make switch initiates the circuit short circuit & master breaker isolates the test device from the source at the end of predetermined time.  If the test device failed to operate, master CB can be tripped. 13 Back up breaker Short Circuit Testing Gen Reactor Test device CT Making Switch Circuit Capacitance G
  • 14. SYNTYHETIC TESTS  Heavy current at low voltage is applied  Recovery voltage is simulated by high voltage, small current source  Procedure: When auxiliary breaker 3 and test circuit breaker T are closed, making switch 4 and master breaker 1 is closed. Hence, Current flows through test CB. At time t0, the test CB begins to operate. 14 1 2 3 4 5 6 Vc Cc C0 Cv IvIc T
  • 15. SYNTHETIC TEST (Contd.,)  At time t1, just before zero of the gen current, the trigger gap 6 closes and high frequency current from capacitance Cv flows through the arc of the gap  At time t2, gen current is zero. Master CB 1 is opened  The current from Cv will flow through test CB and full voltage will be available  At the instant of breaking, the source is disconnected as the high voltage is supplied by auxiliary CB 4. 15 1 2 3 4 5 6 Vc Cc C0 Cv IvIc T
  • 16. 16
  翻译: