“When Welds Are Too Close: What Happens When You Break the Code or Standard Rule — And How to Engineer a Way out."
What really happens when welds are placed too close — and the 5t rule is ignored (ASME B31.3 requirement)?
In one of our recent brownfield projects, a seemingly small deviation from ASME B31.3 led to plastic deformation, stress concentration, and a costly redesign.
In this post, I’m sharing the full story — what went wrong, how we diagnosed it with nonlinear FEA, and how we engineered a practical and verifiable safeguard to fix it.
🔹 For full context, check out these two companion articles — highly recommended to read in parallel:
📌 The Problem: Weld Spacing Violation on a 6” Line in a Brownfield Retrofit
In a brownfield upgrade project inside an aging gas dehydration unit, we had to install a new 6” Sch. 80 CS line to re-route glycol return flow. Due to physical limitations of the existing structure — including structural steel, cable trays, and a nearby vessel — the spool design left only ~18 mm of straight pipe between two girth welds.
According to ASME B31.3, the recommended minimum distance between adjacent butt welds is 5 times the wall thickness (in this case: 5 × 10.97 mm ≈ 55 mm), unless engineering justification is provided.
Unfortunately, in this case:
But hydrotest doesn’t account for long-term cyclic thermal loading or residual stress interaction in overlapping HAZs.
⚠️ The Result: Localized Deformation & Stress Hotspots After Startup
Roughly 3–4 weeks into commissioning:
Key contributing factors:
🔬 The Diagnosis: Nonlinear FEA in ANSYS Reveals the Root Cause
The pipe section was modeled in ANSYS using:
Results showed:
FEA confirmed ratcheting behavior due to weld proximity and repeated expansion in an overstressed zone.
💪 The Fix: Engineering Safeguards in Action
Once the failure mechanism was identified, a multi-step safeguarding strategy was implemented. Each action was carefully engineered, verified, and documented:
Recommended by LinkedIn
2. Local Post-Weld Heat Treatment (PWHT)
3. Updated FEA with Revised Conditions
4. Engineering Justification & Documentation
- Stress reports
- Modified isometric drawings
- Weld maps and NDT
- PWHT logs and thermal graphs
5. Formal Client Approval Process
🧠 The Lesson: Safeguarding Is a Must, Not a Choice
This was not simply about spacing. It was a case where field constraints pushed us outside the code envelope — and safeguarding became the only acceptable path forward.
ASME B31.3 allows for flexibility, but only if adequate safeguards are in place. As explained in detail in this article, safeguarding is the provision of protective measures to minimize the risk of accidental damage to the piping or to minimize the harmful consequences of possible piping failure.
It is a concept that works well in the context of the B31.3 Section because the owner has overall responsibility for all aspects (design and operation) of the piping system. This differs from the much more limited scope of responsibilities in ASME B31.1 and ASME BPVC, Section VIII, Division 1.
Designers should note that, based on B31.3, the owner also has the ability to effectively specify and implement safeguarding provisions. For example, ASME B31.3 permits the use of certain components, joining methods, and procedures when appropriate safeguards are provided. One classic example: brazed joints are normally prohibited in flammable/toxic service unless safeguarded (para. 317.2).
In our case, the safeguarding strategy was not just a fix — it was a structured engineering response to a real-world constraint. Without it, the risk of failure remained unacceptably high.
Whenever you are forced to go below code minimums, you must: ✅ Analyze the failure modes ✅ Design appropriate safeguards ✅ Justify and document the changes ✅ Obtain formal client approval
This mindset ensures integrity — not just compliance.
📣 Final Thought
Codes give us the minimums. Projects often force us below them. What matters is how we respond.
Have you ever engineered your way out of a code violation? Share your experience.
Let’s learn, build safer systems, and lead with engineering judgment.
#WeldSpacing #ASME #B313 #Safeguarding #FEA #FieldEngineering #PlasticDeformation #CodeViolation #EngineeringJudgment #OilAndGas #PipingDesign #BrownfieldProjects #StressAnalysis
instrumentation and control engineer | electronics engineer
2wThanks for sharing, Seyed
Principal Engineer @ McDermott International, Ltd. | Chartered Engineer
2wThe approach in solving the engineering problem was good. Understanding the problem, Simulating the behavior, performing FEA and getting results close to real situation was the key takeaway. Giving a great solution exhibits the confidence of the teamwork. Thanks for sharing.
Project Coordinator - Mechanical Design & Engg, Piping Professional (Offshore Well Head/Process/FPSO's)
2wHelpful insight, Seyed Mohammad
Senior Pipe Stress Engineer
3wThoughtful post, thanks Seyed Mohammad. Even pipe stress analyst need to look in this aspect also.
Reliability Engineer en Repsol
3wgreat insight, thanks for sharing