SlideShare a Scribd company logo
International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016
DOI : 10.5121/ijfls.2016.6204 53
A COUNTEREXAMPLE TO THE FORWARD
RECURSION IN FUZZY CRITICAL PATH
ANALYSIS UNDER DISCRETE FUZZY SETS
Matthew J. Liberatore1
1
Department of Management and Operations, Villanova School of Business, Villanova
University, Villanova, PA 19085
ABSTRACT
Fuzzy logic is an alternate approach for quantifying uncertainty relating to activity duration. The fuzzy
version of the backward recursion has been shown to produce results that incorrectly amplify the level of
uncertainty. However, the fuzzy version of the forward recursion has been widely proposed as an
approach for determining the fuzzy set of critical path lengths. In this paper, the direct application of the
extension principle leads to a proposition that must be satisfied in fuzzy critical path analysis. Using a
counterexample it is demonstrated that the fuzzy forward recursion when discrete fuzzy sets are used to
represent activity durations produces results that are not consistent with the theory presented. The
problem is shown to be the application of the fuzzy maximum. Several methods presented in the literature
are described and shown to provide results that are consistent with the extension principle.
KEYWORDS
critical path analysis, discrete fuzzy sets, forward recursion, counterexample, project scheduling
1. INTRODUCTION
CPM or the critical path method [11] has been successfully applied to plan and control projects
that are organized as a set of inter-related activities. PERT or Program Evaluation and Review
Technique [16] and Monte Carlo simulation apply probability analysis to address situations where
there is uncertainty related to activity duration. PERT models uncertainty by collecting
optimistic, most likely and pessimistic duration estimates of all activities and makes certain
assumptions about the underlying probability distributions. Since the basic version of PERT
tends to underestimate the expected minimum project duration [15]. Monte Carlo simulation is
often preferred in practice when activity durations are uncertain.
However, the information required to estimate probabilities related to activity duration may not
always be known. Fuzzy logic is an alternative approach for measuring uncertainty related to
activity duration. Fuzzy logic measures imprecision or vagueness in estimation, and may be
preferred to probability theory in those situations where past data concerning activity duration is
either unavailable or not relevant, the definition of the activity itself is somewhat unclear, or the
International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016
54
notion of the activity’s completion is vague. Many authors including Chanas and colleagues have
investigated the situation when activity duration can be described by fuzzy numbers [1], [2], [3],
5], [6], [7].
The dominant approach presented in the fuzzy critical path analysis literature is the fuzzy
extension of the forward and backward recursions taken in the project network. This approach
computes the earliest and latest start and finish times and slack, where the maximum, minimum,
addition, and subtraction operators are replaced by their fuzzy counterparts. The application of
the forward recursion with fuzzy activity times was first demonstrated in [3]. In a review of the
fuzzy critical path analysis literature two approaches are described for applying the forward
recursion [4]. They also indicate that the application of the backward recursion would cause a
considerable increase in the range of uncertainty in the start and finish times that are calculated.
These authors present a modification of the backward recursion that has been proposed to
eliminate this disadvantage [12]. Some authors directly apply the backward recursion, while other
authors have proposed different approaches for modifying the backward pass when the activity
times are fuzzy [18], [19], [20], [22]. The backward recursion was found not to compute the sets
of the possible values of the latest starting times and floats of activities [22]. In a stream of
research that uses the joint possibility distribution of activity durations, several authors [8], [9]
have conducted preliminary work for computing fuzzy latest starting times and fuzzy floats,
especially for series-parallel graphs. Polynomial algorithms for determining the intervals of the
latest starting times in the general project network are presented in [22].
Unlike the fuzzy backward recursion, the use of the fuzzy forward recursion is generally accepted
in the literature as providing correct results. As mentioned by several authors [3], [10], [18], [19],
the forward recursion is correct on problems involving fuzzy intervals. The purpose of this paper
is to prove that the fuzzy forward recursion when discrete fuzzy sets are used to represent activity
durations provides results that are not consistent with the direct application of the extension
principle to the critical path problem.
In section 2, we present some background on fuzzy sets and the supporting concepts needed in
the remainder of the paper. In section 3 we provide some brief background on project network
analysis under the assumption that activity durations are certain. Section 4 presents an important
result for fuzzy critical path analysis based on the extension principle. In section 5 the
counterexample to the application of the fuzzy forward recursion is presented and the reason the
results are not consistent with the extension principle is shown. Section 6 discusses two proposed
approaches from the literature that present results consistent with the extension principle.
Conclusions are offered in section 7.
2. FUZZY SETS
Following [17] we give the following definitions of a fuzzy set, fuzzy quantity and the support
set:
Definition 1. A fuzzy set M is a subset of the universe U that is characterized by a membership
function Mµ : U→[0,1] such that:
International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016
55
( )M xµ = 0, if x certainly is not a member of M,
( )M xµ = 1, if x certainly is a member of M,
( ) (0,1)M xµ ∈ , if it is uncertain whether x is a member of M, where ( )M xµ represents the
degree to which x is a member of M.
Now assume that activity duration is uncertain due to vagueness or imprecision and is a fuzzy
quantity defined as follows:
Definition 2. A fuzzy quantity M is a fuzzy subset of with membership function
[ ]: 0,1Mµ → such that
sup( ( ) : ) 1M x xµ ∈ = (1a)
( )
1 2 1 2
1 2
, , : ,
, ( ) 0
M M M M
M M
M
x x x x x
x x x xµ
∃ ∈ < ∀ ∈
∉ ⇒ =
(1b)
Definition 3. The support set of Mµ is defined as { }| ( ) 0M MS x xµ= ∈ > .
This definition can include discrete as well as continuous fuzzy sets, such as those that are
triangular or trapezoidal in shape. If the support set MS is finite, condition (1a) above can be
replaced with 0 0: ( ) 1Mx xµ∃ ∈ = . To simplify the presentation, we will assume this condition
hereafter. Condition (1b) implies that the support set is bounded. We will also assume that the
support set is discrete. Let iS be the support set of ia , where , , 1,2,...,i k i it S k n∈ = . That is, ia
has in possible non-zero discrete durations ,i kt in its support set iS .
As an example of a fuzzy activity duration, the vague statement that the duration of activity ia is
“about six weeks” might be represented by the following fuzzy quantity
~
it whose membership
function will be denoted as: (6) .7, (7) 1.0, (8) .8, ( ) 0i i i i itµ µ µ µ= = = = , otherwise. We can
also denote this membership function as 6/0.7, 7/1.0, 8/0.8.
We also need to define fuzzy addition and the fuzzy maximum of fuzzy quantities. Let 1M and
2M be fuzzy quantities with membership functions 1Mµ and 2Mµ , respectively. Following [17]
and as a direct application of the extension principle:
Definition 4. Fuzzy Addition: The membership function for the fuzzy quantity 21 MM ⊕ is
defined as:
)(21
zMM ⊕µ = Max Min { }1 2
( ), ( )M Mx yµ µ (2)
International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016
56
z x y= +
Definition 5. Fuzzy Maximum: The membership function for the fuzzy quantity max (M1, M2)
is defined as:
1 2max( , ) ( )M M zµ = Max Min { }1 2
( ), ( )M Mx yµ µ (3)
max( , )z x y=
One final definition is needed:
Definition 6: A configuration Ω is defined as a precise instantiation of the duration of all ia Aε .
In the next section we provide the necessary background on project network analysis.
3. BACKGROUND ON PROJECT NETWORKS AND THE CRITICAL
PATH
Let { }1 2,, ..., NA a a a= be the set of project activities. Let iB , i=1,2,…,N, iB A⊂ , be defined so
that the elements of iB are the immediate predecessors of ia . We let { }1 2, ,..., NB B B B= be the
set of predecessor sets. Cycles of activities within the project network are not allowed. We
assume that 1a is the only element of A such that 1B = ∅. We also assume Na is the only element
of A such that .N ia B i N∉ ∀ ≠ If the project network does not have unique start and finish
activities, we add dummy activities (which have zero duration) for this purpose. Taken together
A and B define the network structure or graph G of a project.
We initially assume that it ∈ , 0it ≥ , is the certain duration for ia , where { }1 2, ,..., NT t t t= . A
path p from start to finish is a finite sequence of activities
{ }1 2
, ,..., sr r ra a a where 1
, 1,2,..., 1k kr ra B k s+
∈ = − , and 1 1ra a= and sr na a= . The length of the
longest path from the start activity to the finish activity is the minimum project completion time.
This path is called the critical path, the activities along it are called critical path activities, and
the length of the path is denoted as CPL . Given G for each unique set of values T we can
compute CPL . Therefore, there is a function f(T|G): ...× × × → that maps T to CPL , or
CPL = f(T|G).
4. FUZZY CRITICAL PATH ANALYSIS
Proposition 1: Fuzzy Critical Path Membership Function
The membership function for the fuzzy set of critical path lengths can be determined as:
International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016
57
( )CP CPLµ = Max Min { }( )i itµ (4)
1 2, ,..., Nt t t { }1,2,...,i N∈
1 2( , ,..., | )N CPf t t t G L=
where ( )CP CPLµ is the membership function for the length of the critical path over the fuzzy
subset CP in ; and for a graph G and activity durations 1 2, ,..., Nt t t ,
1 2( , ,..., | )Nf t t t G determines the length of the critical path.
Proof: direct application of the extension principle of fuzzy logic [21] using maximum and
minimum for the disjunction and conjunction operators, respectively.
Because Proposition 1 represents the direct generalization of critical path analysis from the crisp
to the fuzzy domain, any proposed fuzzy critical path analysis approach should provide results
that are consistent with it.
One approach for implementing Proposition 1 requires defining all possible configurations,
determining the belief of each configuration as the minimum of the beliefs associated with all
activity durations included in this configuration, and then determining the maximum belief of all
configurations leading to each possible critical path length. The results form the fuzzy set of
critical path lengths.
5. COUNTER EXAMPLE TO THE FUZZY FORWARD RECURSION
In standard CPM the earliest start (ESi) and earliest finish (EFi) of an activity are defined as:
ESi = max EFj (5)
ij B∈
where we set ES0 = 0, and
EFi = ESi + it (6)
As defined in section 3 activity N does not have any successors, and so EFN is the length of the
critical path.
Assuming it% is a fuzzy quantity representing the duration of ia , the fuzzy earliest start iES and
fuzzy earliest finish iEF are defined as follows:
maxi jES EF= (7)
ij B∈
International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016
58
i i iEF ES t= ⊕% (8)
where max and ⊕ represent the extended fuzzy maximum and fuzzy addition, respectively, as
given in definitions 4 and 5.
Proposition 2: The fuzzy forward recursion does not always yield membership functions for the
fuzzy set of critical path lengths that are consistent with Proposition 1.
Proof: By counterexample using the data from a simple series – parallel graph (these graphs are
defined in [8] as shown in Figure 1. In this example there 2*3*3*1 = 18 configurations as shown
in Table 1. For each configuration, we determine the lengths of all paths, identify the critical
path, and following Proposition 1 determine the configuration belief as the minimum of the
beliefs of the possible activity durations. We combine the configurations by taking the maximum
of the beliefs over all configurations having the same critical path length. From Table 1 the fuzzy
set of critical path lengths is shown to be:
( )CP CPLµ = 6/0.1, 7/0.2, 8/0.5, 9/0.2, 10/0.5, 11/0.1, 12/1 (9)
The fuzzy forward recursion is applied using equations (5) and (6), with fuzzy addition and fuzzy
maximum as defined in equations (2) and (3), respectively. The results are as follows:
1ES = 0/1 (10)
1EF = 0/1 ⊕ (3/0.5, 5/1) = 3/0.5, 5/1 (11)
2ES = 1EF = 3/0.5, 5/1 (12)
2EF = (3/0.5, 5/1) ⊕ (3/0.2, 5/0.5, 7/1) = 6/0.2, 8/0.5, 10/0.5, 12/1 (13)
3ES = 1EF = 3/0.5, 5/1 (14)
3EF = (3/0.5, 5/1) ⊕ (2/0.1, 4/1, 6/0.1) = 5/0.1, 7/0.5, 9/1, 11/0.1 (15)
4ES = max { 2EF , 3EF } (16)
= max {(6/0.2, 8/0.5, 10/0.5, 12/1), (5/0.1, 7/0.5, 9/1, 11/0.1)}
= 6/0.1, 7/0.2, 8/0.5, 9/0.5, 10/0.5, 11/0.1, 12/1
4EF = (6/0.1, 7/0.2, 8/0.5, 9/0.5, 10/0.5, 11/0.1, 12/1) ⊕ 0/1 (17)
= 6/0.1, 7/0.2, 8/0.5, 9/0.5, 10/0.5, 11/0.1, 12/1
where 4EF is by definition ( )CP CPLµ , the fuzzy set of critical path lengths.
International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016
59
A comparison of equations (9) and (17) show that the range of possible critical path lengths is the
same, but that the belief of the possible critical path length of 9 is 0.2 in equation (9) and 0.5 in
equation (17). This difference proves the assertion.
Discussion: The forward algorithm is generally regarded as providing correct results in the
literature, with no distinction made for activity durations represented as discrete fuzzy sets. The
difference in the belief for the possible critical path length of 9 from Example 1 results from
incorrect comparisons made in the computation of the fuzzy maximum of the earliest finishes.
Specifically, the fuzzy maximum incorrectly compares earliest finish values that are based on
activity durations from different configurations. These configurations differ in terms of the
possible values of the activity that is the immediate predecessor of those activities whose earliest
finishes are being compared.
For example, in equation (16) the possible time 8/0.5 from 2EF is compared with the possible
time 9/1 from 3EF to yield 9/0.5. Folding back, in equation (13) the possible duration 8/0.5
results from the addition of 3/0.5 from 1EF and 5/0.5 from the possible duration of 2a . Since
the 1ES is 0, 3/0.5 is the possible duration of 1a . In equation (15) the possible duration 9/1 results
from the addition of 5/1 from 1EF and 4/1 from the possible duration of 3a . Since the 1ES is 0,
5/1 is the possible duration of 1a . That is, different possible durations of 1a are used to obtain the
possible time 8/0.5 from 2EF and the possible time 9/1 from 3EF . Thus, the fuzzy maximum
incorrectly compares earliest finishes that are based on activity durations from different
configurations. In the example above, if the possible duration of 1a were 3/0.2 instead of 3/0.5,
then the fuzzy forward recursion would have produced the correct result, simply because of the
specific value of a belief. However, since the fuzzy maximum is used repeatedly in the
application of the fuzzy forward recursion, errors are likely to occur in many, if not most,
problems.
6.PROPOSED CRITICAL PATH METHODS THAT ARE
CONSISTENT WITH THE EXTENSION PRINCIPLE
This author has proposed several alternative approaches for computing the fuzzy set of critical
path lengths that are consistent with the extension principle and Proposition 2. The first approach
[13] is based on the idea that rather than enumerate all possible configurations, generate and then
analyze a small number of configurations to achieve convergence to the membership function of
the fuzzy set of critical path lengths. This method uses pseudo-random numbers to select possible
durations for each activity to form configurations. Either the standard forward pass or path
enumeration can be applied to determine the critical path length of a configuration. Following
Proposition 1, the belief associated with the possible critical path length of a given configuration
is the minimum of the beliefs of the possible activity durations in the configuration. Since several
configurations may lead to the same possible critical path length, again following Proposition 1
and the extension principle, the belief of a possible critical path length is the maximum of the
beliefs associated with all possible critical path lengths of the same duration. Additional
International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016
60
configurations are analyzed until the percentage change in AREA (sum of the products of all
possible critical path lengths and their beliefs) is less than some tolerance. The proposed method
is evaluated using a series of test problems from the literature.
The second approach [14] begins by using a standard forward-backward pass algorithm to
compute the minimum possible critical path length, using the smallest possible duration for each
activity. A similar approach determines the maximum possible critical path length. Following
Proposition 1 a mathematical programming problem is formulated, whose objective is to
determine the belief associated with a possible critical path length. This mathematical program is
run for all possible critical path lengths, ranging between the possible minimum and maximum
lengths. In this way, the membership function for the fuzzy set of critical path lengths is
constructed. The proposed method is evaluated using a series of test problems from the literature.
7. CONCLUSIONS
In this paper, the direct application of the extension principle leads to a proposition that must be
satisfied in fuzzy critical path analysis. Using a counterexample where discrete fuzzy sets are
used to represent activity durations, it is demonstrated that the fuzzy forward recursion produces
results that are not consistent with the theory presented. The problem is shown to be the
application of the fuzzy maximum, since it compares earliest finishes that are based on activity
durations from different configurations. Several methods offered in the literature that provide
results consistent with the extension principle are described. The development of more efficient
algorithms to compute the fuzzy set of critical path lengths is an area of further research.
Figure 1. Example network with fuzzy activity durations
International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016
61
Table 1: Applying proposition 1 to the example
Activity 1 Activity 2 Activity 3 P 1 - 2 - 4 P 1 - 3 - 4 Critical Path CP fuzzy set
Duration Belief Duration Belief Duration Belief Duration Duration Duration Belief Duration Belief
3 0.5 3 0.2 2 0.1 6 5 6 0.1 6 0.1
3 0.5 3 0.2 4 1 6 7 7 0.2 7 0.2
3 0.5 3 0.2 6 0.1 6 9 9 0.1 8 0.5
3 0.5 5 0.5 2 0.1 8 5 8 0.1 9 0.2
3 0.5 5 0.5 4 1 8 7 8 0.5 10 0.5
3 0.5 5 0.5 6 0.1 8 9 9 0.1 11 0.1
3 0.5 7 1 2 0.1 10 5 10 0.1 12 1
3 0.5 7 1 4 1 10 7 10 0.5
3 0.5 7 1 6 0.1 10 9 10 0.1
5 1 3 0.2 2 0.1 8 7 8 0.1
5 1 3 0.2 4 1 8 9 9 0.2
5 1 3 0.2 6 0.1 8 11 11 0.1
5 1 5 0.5 2 0.1 10 7 10 0.1
5 1 5 0.5 4 1 10 9 10 0.5
5 1 5 0.5 6 0.1 10 11 11 0.1
5 1 7 1 2 0.1 12 7 12 0.1
5 1 7 1 4 1 12 9 12 1
5 1 7 1 6 0.1 12 11 12 0.1
*activity 4 is a dummy whose duration is certainly 0
REFERENCES
[1] Chanas, S. (1982) “Fuzzy sets in few classical operational research problems” in Gupta M. &
Sanches, E. (eds.), Approximate Reasoning in Decision Analysis, North-Holland Publishing
Company, pp. 351-361.
[2] Chanas, S., Dubois, D. & Zielinksi, P. (2002) “On the sure criticality of tasks in activity networks
with imprecise durations”, IEEE Transactions on Systems, Man, and Cybernetics – Part B:
Cybernetics, Vol. 32, pp. 393-407.
[3] Chanas, S. & Kamburowski, J. (1981) “The use of fuzzy variables in PERT”, Fuzzy Sets and
Systems, Vol. 1, pp. 11 – 19.
[4] Chanas, S. & Kuchta, D. (1998) “Discrete fuzzy optimization”, Chapter 8 in Slowinski, R. (ed.),
Fuzzy sets in Decision Analysis, Operations Research and Statistics, Kluwer Academic Publishers,
Boston, pp. 249-280.
[5] Chanas, S. & Zielinski, P. (2001) “Critical path analysis in the network with fuzzy activity times”,
Fuzzy Sets and Systems, Vol. 122, pp. 195-204.
[6] Chanas, S. & Zielinski, P. (2002) “The computational complexity of the criticality problems in a
network with interval activity times”, European Journal of Operational Research, Vol. 136, pp. 541 –
550.
[7] Chanas, S. & Zielinski, P. (2003) “On the hardness of evaluating criticality of activities in a planar
network with duration intervals”, Operations Research Letters, Vol. 31, pp. 53 – 59.
[8] Dubois, D., Fargier, H. & Galvagnon, V. (2003) “On the latest starting times and floats in activity
networks with ill-known durations”, European Journal of Operational Research, Vol. 147, pp. 266-
280.
[9] Fargier, H., Galvagnon, V. & Dubois, D. (2000) “Fuzzy PERT in series-parallel graphs”, in Ninth
IEEE International Conference on Fuzzy Systems, San Antonio, TX, pp. 717-722.
International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016
62
[10] Hapke, M., & Slowinski, R. (1996) “Fuzzy priority heuristics for project scheduling”, Fuzzy Sets and
Systems, Vol. 83, pp. 291-299.
[11] Kelley, J. (1961) “Critical path planning and scheduling -- mathematical basis”, Operations Research,
Vol. 9, pp. 296-320.
[12] Kamburowski, J. (1983) “Fuzzy activity duration times in critical path analysis”, International
Symposium on Project Management, New Delhi, pp. 194-199.
[13] Liberatore, M. (2007) “A latin hypercube sampling approach for fuzzy critical path analysis”,
International Journal of Operations and Quantitative Management, Vol. 13, No. 4, pp. 235 – 250.
[14] Liberatore, M. (2008) ”Critical path analysis with fuzzy activity times”, IEEE Transactions on
Engineering Management, Vol. 55, No. 2, pp. 329 - 337.
[15] Lootsma, F. A. (1989) “Stochastic and fuzzy PERT”, European Journal of Operational Research, Vol.
43, pp. 174-183.
[16] Malcolm, D., Rosenbloom, J., Clark, C. & and Fazar, W. (1959) “Application of a technique for
research and development project evaluation”, Operations Research, Vol. 7, pp. 646-669.
[17] Mares, M. (1994) Computation Over Fuzzy Quantities, CRC Press, Boca Raton.
[18] Nasution, S. (1994) “Fuzzy critical path method”, IEEE Transactions on Systems, Man, and
Cybernetics, Vol. 24, pp. 48-57.
[19] Rommelfanger, H. (1994) “Network analysis and information flow in fuzzy environment”, Fuzzy Sets
and Systems, Vol. 67, pp. 119-128.
[20] Slyeptsov, A. & Tyschchuk, T. (2003) “A method of computation of characteristics of operations in a
problem of fuzzy network planning and management”, Cybernetics and Systems Analysis, Vol. 39,
pp. 367 – 378.
[21] Zadeh, L. (1975) “Calculus of fuzzy restrictions”, in Zadeh, L., Fu, K., Tanaka, K. & Shimara, J.
(eds.), Fuzzy Sets and Their Application to Cognitive and Decision Processes, Academic Process, pp.
1-39.
[22] Zielinski, P. (2005) “On computing the latest starting times and floats of activities in a network with
imprecise durations”, Fuzzy Sets and Systems, Vol. 150, pp. 53 – 76.

More Related Content

What's hot (20)

InternshipReport
InternshipReportInternshipReport
InternshipReport
Hamza Ameur
 
I046850
I046850I046850
I046850
math and computer science
 
HEATED WIND PARTICLE’S BEHAVIOURAL STUDY BY THE CONTINUOUS WAVELET TRANSFORM ...
HEATED WIND PARTICLE’S BEHAVIOURAL STUDY BY THE CONTINUOUS WAVELET TRANSFORM ...HEATED WIND PARTICLE’S BEHAVIOURAL STUDY BY THE CONTINUOUS WAVELET TRANSFORM ...
HEATED WIND PARTICLE’S BEHAVIOURAL STUDY BY THE CONTINUOUS WAVELET TRANSFORM ...
cscpconf
 
50120130406039
5012013040603950120130406039
50120130406039
IAEME Publication
 
ssc_icml13
ssc_icml13ssc_icml13
ssc_icml13
Guy Lebanon
 
Numerical solution of fuzzy hybrid differential equation by third order runge...
Numerical solution of fuzzy hybrid differential equation by third order runge...Numerical solution of fuzzy hybrid differential equation by third order runge...
Numerical solution of fuzzy hybrid differential equation by third order runge...
Alexander Decker
 
11.[8 17]numerical solution of fuzzy hybrid differential equation by third or...
11.[8 17]numerical solution of fuzzy hybrid differential equation by third or...11.[8 17]numerical solution of fuzzy hybrid differential equation by third or...
11.[8 17]numerical solution of fuzzy hybrid differential equation by third or...
Alexander Decker
 
11.numerical solution of fuzzy hybrid differential equation by third order ru...
11.numerical solution of fuzzy hybrid differential equation by third order ru...11.numerical solution of fuzzy hybrid differential equation by third order ru...
11.numerical solution of fuzzy hybrid differential equation by third order ru...
Alexander Decker
 
Ee35741744
Ee35741744Ee35741744
Ee35741744
IJERA Editor
 
On a Deterministic Property of the Category of k-almost Primes: A Determinist...
On a Deterministic Property of the Category of k-almost Primes: A Determinist...On a Deterministic Property of the Category of k-almost Primes: A Determinist...
On a Deterministic Property of the Category of k-almost Primes: A Determinist...
Ramin (A.) Zahedi
 
An_Accelerated_Nearest_Neighbor_Search_Method_for_the_K-Means_Clustering_Algo...
An_Accelerated_Nearest_Neighbor_Search_Method_for_the_K-Means_Clustering_Algo...An_Accelerated_Nearest_Neighbor_Search_Method_for_the_K-Means_Clustering_Algo...
An_Accelerated_Nearest_Neighbor_Search_Method_for_the_K-Means_Clustering_Algo...
Adam Fausett
 
Master's thesis
Master's thesisMaster's thesis
Master's thesis
Smrati Kumar Katiyar
 
llorma_jmlr copy
llorma_jmlr copyllorma_jmlr copy
llorma_jmlr copy
Guy Lebanon
 
lcr
lcrlcr
lcr
Guy Lebanon
 
Analysis of CANADAIR CL-215 retractable landing gear.
Analysis of CANADAIR CL-215 retractable landing gear.Analysis of CANADAIR CL-215 retractable landing gear.
Analysis of CANADAIR CL-215 retractable landing gear.
Nagesh NARASIMHA PRASAD
 
Parellelism in spectral methods
Parellelism in spectral methodsParellelism in spectral methods
Parellelism in spectral methods
Ramona Corman
 
Dce a novel delay correlation
Dce a novel delay correlationDce a novel delay correlation
Dce a novel delay correlation
ijdpsjournal
 
Fortran induction project. DGTSV DGESV
Fortran induction project. DGTSV DGESVFortran induction project. DGTSV DGESV
Fortran induction project. DGTSV DGESV
Nagesh NARASIMHA PRASAD
 
Advances in composite integer factorization
Advances in composite integer factorizationAdvances in composite integer factorization
Advances in composite integer factorization
Alexander Decker
 
On selection of periodic kernels parameters in time series prediction
On selection of periodic kernels parameters in time series predictionOn selection of periodic kernels parameters in time series prediction
On selection of periodic kernels parameters in time series prediction
csandit
 
InternshipReport
InternshipReportInternshipReport
InternshipReport
Hamza Ameur
 
HEATED WIND PARTICLE’S BEHAVIOURAL STUDY BY THE CONTINUOUS WAVELET TRANSFORM ...
HEATED WIND PARTICLE’S BEHAVIOURAL STUDY BY THE CONTINUOUS WAVELET TRANSFORM ...HEATED WIND PARTICLE’S BEHAVIOURAL STUDY BY THE CONTINUOUS WAVELET TRANSFORM ...
HEATED WIND PARTICLE’S BEHAVIOURAL STUDY BY THE CONTINUOUS WAVELET TRANSFORM ...
cscpconf
 
Numerical solution of fuzzy hybrid differential equation by third order runge...
Numerical solution of fuzzy hybrid differential equation by third order runge...Numerical solution of fuzzy hybrid differential equation by third order runge...
Numerical solution of fuzzy hybrid differential equation by third order runge...
Alexander Decker
 
11.[8 17]numerical solution of fuzzy hybrid differential equation by third or...
11.[8 17]numerical solution of fuzzy hybrid differential equation by third or...11.[8 17]numerical solution of fuzzy hybrid differential equation by third or...
11.[8 17]numerical solution of fuzzy hybrid differential equation by third or...
Alexander Decker
 
11.numerical solution of fuzzy hybrid differential equation by third order ru...
11.numerical solution of fuzzy hybrid differential equation by third order ru...11.numerical solution of fuzzy hybrid differential equation by third order ru...
11.numerical solution of fuzzy hybrid differential equation by third order ru...
Alexander Decker
 
On a Deterministic Property of the Category of k-almost Primes: A Determinist...
On a Deterministic Property of the Category of k-almost Primes: A Determinist...On a Deterministic Property of the Category of k-almost Primes: A Determinist...
On a Deterministic Property of the Category of k-almost Primes: A Determinist...
Ramin (A.) Zahedi
 
An_Accelerated_Nearest_Neighbor_Search_Method_for_the_K-Means_Clustering_Algo...
An_Accelerated_Nearest_Neighbor_Search_Method_for_the_K-Means_Clustering_Algo...An_Accelerated_Nearest_Neighbor_Search_Method_for_the_K-Means_Clustering_Algo...
An_Accelerated_Nearest_Neighbor_Search_Method_for_the_K-Means_Clustering_Algo...
Adam Fausett
 
llorma_jmlr copy
llorma_jmlr copyllorma_jmlr copy
llorma_jmlr copy
Guy Lebanon
 
Analysis of CANADAIR CL-215 retractable landing gear.
Analysis of CANADAIR CL-215 retractable landing gear.Analysis of CANADAIR CL-215 retractable landing gear.
Analysis of CANADAIR CL-215 retractable landing gear.
Nagesh NARASIMHA PRASAD
 
Parellelism in spectral methods
Parellelism in spectral methodsParellelism in spectral methods
Parellelism in spectral methods
Ramona Corman
 
Dce a novel delay correlation
Dce a novel delay correlationDce a novel delay correlation
Dce a novel delay correlation
ijdpsjournal
 
Advances in composite integer factorization
Advances in composite integer factorizationAdvances in composite integer factorization
Advances in composite integer factorization
Alexander Decker
 
On selection of periodic kernels parameters in time series prediction
On selection of periodic kernels parameters in time series predictionOn selection of periodic kernels parameters in time series prediction
On selection of periodic kernels parameters in time series prediction
csandit
 

Similar to A Counterexample to the Forward Recursion in Fuzzy Critical Path Analysis Under Discrete Fuzzy Sets (20)

presentation_final
presentation_finalpresentation_final
presentation_final
Sushanta Roy
 
PREDICTIVE EVALUATION OF THE STOCK PORTFOLIO PERFORMANCE USING FUZZY CMEANS A...
PREDICTIVE EVALUATION OF THE STOCK PORTFOLIO PERFORMANCE USING FUZZY CMEANS A...PREDICTIVE EVALUATION OF THE STOCK PORTFOLIO PERFORMANCE USING FUZZY CMEANS A...
PREDICTIVE EVALUATION OF THE STOCK PORTFOLIO PERFORMANCE USING FUZZY CMEANS A...
ijfls
 
An Improved Adaptive Multi-Objective Particle Swarm Optimization for Disassem...
An Improved Adaptive Multi-Objective Particle Swarm Optimization for Disassem...An Improved Adaptive Multi-Objective Particle Swarm Optimization for Disassem...
An Improved Adaptive Multi-Objective Particle Swarm Optimization for Disassem...
IJRESJOURNAL
 
Critical Paths Identification on Fuzzy Network Project
Critical Paths Identification on Fuzzy Network ProjectCritical Paths Identification on Fuzzy Network Project
Critical Paths Identification on Fuzzy Network Project
iosrjce
 
Integration techniques for two dimensional domains
Integration techniques for two dimensional domainsIntegration techniques for two dimensional domains
Integration techniques for two dimensional domains
eSAT Publishing House
 
A High Order Continuation Based On Time Power Series Expansion And Time Ratio...
A High Order Continuation Based On Time Power Series Expansion And Time Ratio...A High Order Continuation Based On Time Power Series Expansion And Time Ratio...
A High Order Continuation Based On Time Power Series Expansion And Time Ratio...
IJRES Journal
 
Fault diagnosis using genetic algorithms and
Fault diagnosis using genetic algorithms andFault diagnosis using genetic algorithms and
Fault diagnosis using genetic algorithms and
eSAT Publishing House
 
F5233444
F5233444F5233444
F5233444
IOSR-JEN
 
P REDICTION F OR S HORT -T ERM T RAFFIC F LOW B ASED O N O PTIMIZED W...
P REDICTION  F OR  S HORT -T ERM  T RAFFIC  F LOW  B ASED  O N  O PTIMIZED  W...P REDICTION  F OR  S HORT -T ERM  T RAFFIC  F LOW  B ASED  O N  O PTIMIZED  W...
P REDICTION F OR S HORT -T ERM T RAFFIC F LOW B ASED O N O PTIMIZED W...
ijcsit
 
Forecasting Gasonline Price in Vietnam Based on Fuzzy Time Series and Automat...
Forecasting Gasonline Price in Vietnam Based on Fuzzy Time Series and Automat...Forecasting Gasonline Price in Vietnam Based on Fuzzy Time Series and Automat...
Forecasting Gasonline Price in Vietnam Based on Fuzzy Time Series and Automat...
IJEID :: International Journal of Excellence Innovation and Development
 
Multi objective predictive control a solution using metaheuristics
Multi objective predictive control  a solution using metaheuristicsMulti objective predictive control  a solution using metaheuristics
Multi objective predictive control a solution using metaheuristics
ijcsit
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
IJERD Editor
 
Fault diagnosis using genetic algorithms and principal curves
Fault diagnosis using genetic algorithms and principal curvesFault diagnosis using genetic algorithms and principal curves
Fault diagnosis using genetic algorithms and principal curves
eSAT Journals
 
The Analysis of Performance Measures of Generalized Trapezoidal Fuzzy Queuing...
The Analysis of Performance Measures of Generalized Trapezoidal Fuzzy Queuing...The Analysis of Performance Measures of Generalized Trapezoidal Fuzzy Queuing...
The Analysis of Performance Measures of Generalized Trapezoidal Fuzzy Queuing...
IJERA Editor
 
J016577185
J016577185J016577185
J016577185
math and computer science
 
On Selection of Periodic Kernels Parameters in Time Series Prediction
On Selection of Periodic Kernels Parameters in Time Series Prediction On Selection of Periodic Kernels Parameters in Time Series Prediction
On Selection of Periodic Kernels Parameters in Time Series Prediction
cscpconf
 
ON SELECTION OF PERIODIC KERNELS PARAMETERS IN TIME SERIES PREDICTION
ON SELECTION OF PERIODIC KERNELS PARAMETERS IN TIME SERIES PREDICTIONON SELECTION OF PERIODIC KERNELS PARAMETERS IN TIME SERIES PREDICTION
ON SELECTION OF PERIODIC KERNELS PARAMETERS IN TIME SERIES PREDICTION
cscpconf
 
How to Decide the Best Fuzzy Model in ANFIS
How to Decide the Best Fuzzy Model in ANFIS How to Decide the Best Fuzzy Model in ANFIS
How to Decide the Best Fuzzy Model in ANFIS
International Journal of Modern Research in Engineering and Technology
 
Fuzzy Fatigue Failure Model to Estimate the Reliability of Extend the Service...
Fuzzy Fatigue Failure Model to Estimate the Reliability of Extend the Service...Fuzzy Fatigue Failure Model to Estimate the Reliability of Extend the Service...
Fuzzy Fatigue Failure Model to Estimate the Reliability of Extend the Service...
IOSRJMCE
 
EDGE DETECTION IN SEGMENTED IMAGES THROUGH MEAN SHIFT ITERATIVE GRADIENT USIN...
EDGE DETECTION IN SEGMENTED IMAGES THROUGH MEAN SHIFT ITERATIVE GRADIENT USIN...EDGE DETECTION IN SEGMENTED IMAGES THROUGH MEAN SHIFT ITERATIVE GRADIENT USIN...
EDGE DETECTION IN SEGMENTED IMAGES THROUGH MEAN SHIFT ITERATIVE GRADIENT USIN...
ijscmcj
 
presentation_final
presentation_finalpresentation_final
presentation_final
Sushanta Roy
 
PREDICTIVE EVALUATION OF THE STOCK PORTFOLIO PERFORMANCE USING FUZZY CMEANS A...
PREDICTIVE EVALUATION OF THE STOCK PORTFOLIO PERFORMANCE USING FUZZY CMEANS A...PREDICTIVE EVALUATION OF THE STOCK PORTFOLIO PERFORMANCE USING FUZZY CMEANS A...
PREDICTIVE EVALUATION OF THE STOCK PORTFOLIO PERFORMANCE USING FUZZY CMEANS A...
ijfls
 
An Improved Adaptive Multi-Objective Particle Swarm Optimization for Disassem...
An Improved Adaptive Multi-Objective Particle Swarm Optimization for Disassem...An Improved Adaptive Multi-Objective Particle Swarm Optimization for Disassem...
An Improved Adaptive Multi-Objective Particle Swarm Optimization for Disassem...
IJRESJOURNAL
 
Critical Paths Identification on Fuzzy Network Project
Critical Paths Identification on Fuzzy Network ProjectCritical Paths Identification on Fuzzy Network Project
Critical Paths Identification on Fuzzy Network Project
iosrjce
 
Integration techniques for two dimensional domains
Integration techniques for two dimensional domainsIntegration techniques for two dimensional domains
Integration techniques for two dimensional domains
eSAT Publishing House
 
A High Order Continuation Based On Time Power Series Expansion And Time Ratio...
A High Order Continuation Based On Time Power Series Expansion And Time Ratio...A High Order Continuation Based On Time Power Series Expansion And Time Ratio...
A High Order Continuation Based On Time Power Series Expansion And Time Ratio...
IJRES Journal
 
Fault diagnosis using genetic algorithms and
Fault diagnosis using genetic algorithms andFault diagnosis using genetic algorithms and
Fault diagnosis using genetic algorithms and
eSAT Publishing House
 
P REDICTION F OR S HORT -T ERM T RAFFIC F LOW B ASED O N O PTIMIZED W...
P REDICTION  F OR  S HORT -T ERM  T RAFFIC  F LOW  B ASED  O N  O PTIMIZED  W...P REDICTION  F OR  S HORT -T ERM  T RAFFIC  F LOW  B ASED  O N  O PTIMIZED  W...
P REDICTION F OR S HORT -T ERM T RAFFIC F LOW B ASED O N O PTIMIZED W...
ijcsit
 
Multi objective predictive control a solution using metaheuristics
Multi objective predictive control  a solution using metaheuristicsMulti objective predictive control  a solution using metaheuristics
Multi objective predictive control a solution using metaheuristics
ijcsit
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
IJERD Editor
 
Fault diagnosis using genetic algorithms and principal curves
Fault diagnosis using genetic algorithms and principal curvesFault diagnosis using genetic algorithms and principal curves
Fault diagnosis using genetic algorithms and principal curves
eSAT Journals
 
The Analysis of Performance Measures of Generalized Trapezoidal Fuzzy Queuing...
The Analysis of Performance Measures of Generalized Trapezoidal Fuzzy Queuing...The Analysis of Performance Measures of Generalized Trapezoidal Fuzzy Queuing...
The Analysis of Performance Measures of Generalized Trapezoidal Fuzzy Queuing...
IJERA Editor
 
On Selection of Periodic Kernels Parameters in Time Series Prediction
On Selection of Periodic Kernels Parameters in Time Series Prediction On Selection of Periodic Kernels Parameters in Time Series Prediction
On Selection of Periodic Kernels Parameters in Time Series Prediction
cscpconf
 
ON SELECTION OF PERIODIC KERNELS PARAMETERS IN TIME SERIES PREDICTION
ON SELECTION OF PERIODIC KERNELS PARAMETERS IN TIME SERIES PREDICTIONON SELECTION OF PERIODIC KERNELS PARAMETERS IN TIME SERIES PREDICTION
ON SELECTION OF PERIODIC KERNELS PARAMETERS IN TIME SERIES PREDICTION
cscpconf
 
Fuzzy Fatigue Failure Model to Estimate the Reliability of Extend the Service...
Fuzzy Fatigue Failure Model to Estimate the Reliability of Extend the Service...Fuzzy Fatigue Failure Model to Estimate the Reliability of Extend the Service...
Fuzzy Fatigue Failure Model to Estimate the Reliability of Extend the Service...
IOSRJMCE
 
EDGE DETECTION IN SEGMENTED IMAGES THROUGH MEAN SHIFT ITERATIVE GRADIENT USIN...
EDGE DETECTION IN SEGMENTED IMAGES THROUGH MEAN SHIFT ITERATIVE GRADIENT USIN...EDGE DETECTION IN SEGMENTED IMAGES THROUGH MEAN SHIFT ITERATIVE GRADIENT USIN...
EDGE DETECTION IN SEGMENTED IMAGES THROUGH MEAN SHIFT ITERATIVE GRADIENT USIN...
ijscmcj
 

Recently uploaded (20)

Applications of Centroid in Structural Engineering
Applications of Centroid in Structural EngineeringApplications of Centroid in Structural Engineering
Applications of Centroid in Structural Engineering
suvrojyotihalder2006
 
Generative AI & Large Language Models Agents
Generative AI & Large Language Models AgentsGenerative AI & Large Language Models Agents
Generative AI & Large Language Models Agents
aasgharbee22seecs
 
Slide share PPT of NOx control technologies.pptx
Slide share PPT of  NOx control technologies.pptxSlide share PPT of  NOx control technologies.pptx
Slide share PPT of NOx control technologies.pptx
vvsasane
 
Prediction of Flexural Strength of Concrete Produced by Using Pozzolanic Mate...
Prediction of Flexural Strength of Concrete Produced by Using Pozzolanic Mate...Prediction of Flexural Strength of Concrete Produced by Using Pozzolanic Mate...
Prediction of Flexural Strength of Concrete Produced by Using Pozzolanic Mate...
Journal of Soft Computing in Civil Engineering
 
Design Optimization of Reinforced Concrete Waffle Slab Using Genetic Algorithm
Design Optimization of Reinforced Concrete Waffle Slab Using Genetic AlgorithmDesign Optimization of Reinforced Concrete Waffle Slab Using Genetic Algorithm
Design Optimization of Reinforced Concrete Waffle Slab Using Genetic Algorithm
Journal of Soft Computing in Civil Engineering
 
Uses of drones in civil construction.pdf
Uses of drones in civil construction.pdfUses of drones in civil construction.pdf
Uses of drones in civil construction.pdf
surajsen1729
 
Lecture - 7 Canals of the topic of the civil engineering
Lecture - 7  Canals of the topic of the civil engineeringLecture - 7  Canals of the topic of the civil engineering
Lecture - 7 Canals of the topic of the civil engineering
MJawadkhan1
 
Construction Materials (Paints) in Civil Engineering
Construction Materials (Paints) in Civil EngineeringConstruction Materials (Paints) in Civil Engineering
Construction Materials (Paints) in Civil Engineering
Lavish Kashyap
 
2.3 Genetically Modified Organisms (1).ppt
2.3 Genetically Modified Organisms (1).ppt2.3 Genetically Modified Organisms (1).ppt
2.3 Genetically Modified Organisms (1).ppt
rakshaiya16
 
Machine Learning basics POWERPOINT PRESENETATION
Machine Learning basics POWERPOINT PRESENETATIONMachine Learning basics POWERPOINT PRESENETATION
Machine Learning basics POWERPOINT PRESENETATION
DarrinBright1
 
Artificial intelligence and machine learning.pptx
Artificial intelligence and machine learning.pptxArtificial intelligence and machine learning.pptx
Artificial intelligence and machine learning.pptx
rakshanatarajan005
 
hypermedia_system_revisit_roy_fielding .
hypermedia_system_revisit_roy_fielding .hypermedia_system_revisit_roy_fielding .
hypermedia_system_revisit_roy_fielding .
NABLAS株式会社
 
Modeling the Influence of Environmental Factors on Concrete Evaporation Rate
Modeling the Influence of Environmental Factors on Concrete Evaporation RateModeling the Influence of Environmental Factors on Concrete Evaporation Rate
Modeling the Influence of Environmental Factors on Concrete Evaporation Rate
Journal of Soft Computing in Civil Engineering
 
Using the Artificial Neural Network to Predict the Axial Strength and Strain ...
Using the Artificial Neural Network to Predict the Axial Strength and Strain ...Using the Artificial Neural Network to Predict the Axial Strength and Strain ...
Using the Artificial Neural Network to Predict the Axial Strength and Strain ...
Journal of Soft Computing in Civil Engineering
 
01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf
01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf
01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf
PawachMetharattanara
 
Control Methods of Noise Pollutions.pptx
Control Methods of Noise Pollutions.pptxControl Methods of Noise Pollutions.pptx
Control Methods of Noise Pollutions.pptx
vvsasane
 
Nanometer Metal-Organic-Framework Literature Comparison
Nanometer Metal-Organic-Framework  Literature ComparisonNanometer Metal-Organic-Framework  Literature Comparison
Nanometer Metal-Organic-Framework Literature Comparison
Chris Harding
 
Transport modelling at SBB, presentation at EPFL in 2025
Transport modelling at SBB, presentation at EPFL in 2025Transport modelling at SBB, presentation at EPFL in 2025
Transport modelling at SBB, presentation at EPFL in 2025
Antonin Danalet
 
Autodesk Fusion 2025 Tutorial: User Interface
Autodesk Fusion 2025 Tutorial: User InterfaceAutodesk Fusion 2025 Tutorial: User Interface
Autodesk Fusion 2025 Tutorial: User Interface
Atif Razi
 
Mode-Wise Corridor Level Travel-Time Estimation Using Machine Learning Models
Mode-Wise Corridor Level Travel-Time Estimation Using Machine Learning ModelsMode-Wise Corridor Level Travel-Time Estimation Using Machine Learning Models
Mode-Wise Corridor Level Travel-Time Estimation Using Machine Learning Models
Journal of Soft Computing in Civil Engineering
 
Applications of Centroid in Structural Engineering
Applications of Centroid in Structural EngineeringApplications of Centroid in Structural Engineering
Applications of Centroid in Structural Engineering
suvrojyotihalder2006
 
Generative AI & Large Language Models Agents
Generative AI & Large Language Models AgentsGenerative AI & Large Language Models Agents
Generative AI & Large Language Models Agents
aasgharbee22seecs
 
Slide share PPT of NOx control technologies.pptx
Slide share PPT of  NOx control technologies.pptxSlide share PPT of  NOx control technologies.pptx
Slide share PPT of NOx control technologies.pptx
vvsasane
 
Uses of drones in civil construction.pdf
Uses of drones in civil construction.pdfUses of drones in civil construction.pdf
Uses of drones in civil construction.pdf
surajsen1729
 
Lecture - 7 Canals of the topic of the civil engineering
Lecture - 7  Canals of the topic of the civil engineeringLecture - 7  Canals of the topic of the civil engineering
Lecture - 7 Canals of the topic of the civil engineering
MJawadkhan1
 
Construction Materials (Paints) in Civil Engineering
Construction Materials (Paints) in Civil EngineeringConstruction Materials (Paints) in Civil Engineering
Construction Materials (Paints) in Civil Engineering
Lavish Kashyap
 
2.3 Genetically Modified Organisms (1).ppt
2.3 Genetically Modified Organisms (1).ppt2.3 Genetically Modified Organisms (1).ppt
2.3 Genetically Modified Organisms (1).ppt
rakshaiya16
 
Machine Learning basics POWERPOINT PRESENETATION
Machine Learning basics POWERPOINT PRESENETATIONMachine Learning basics POWERPOINT PRESENETATION
Machine Learning basics POWERPOINT PRESENETATION
DarrinBright1
 
Artificial intelligence and machine learning.pptx
Artificial intelligence and machine learning.pptxArtificial intelligence and machine learning.pptx
Artificial intelligence and machine learning.pptx
rakshanatarajan005
 
hypermedia_system_revisit_roy_fielding .
hypermedia_system_revisit_roy_fielding .hypermedia_system_revisit_roy_fielding .
hypermedia_system_revisit_roy_fielding .
NABLAS株式会社
 
01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf
01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf
01.คุณลักษณะเฉพาะของอุปกรณ์_pagenumber.pdf
PawachMetharattanara
 
Control Methods of Noise Pollutions.pptx
Control Methods of Noise Pollutions.pptxControl Methods of Noise Pollutions.pptx
Control Methods of Noise Pollutions.pptx
vvsasane
 
Nanometer Metal-Organic-Framework Literature Comparison
Nanometer Metal-Organic-Framework  Literature ComparisonNanometer Metal-Organic-Framework  Literature Comparison
Nanometer Metal-Organic-Framework Literature Comparison
Chris Harding
 
Transport modelling at SBB, presentation at EPFL in 2025
Transport modelling at SBB, presentation at EPFL in 2025Transport modelling at SBB, presentation at EPFL in 2025
Transport modelling at SBB, presentation at EPFL in 2025
Antonin Danalet
 
Autodesk Fusion 2025 Tutorial: User Interface
Autodesk Fusion 2025 Tutorial: User InterfaceAutodesk Fusion 2025 Tutorial: User Interface
Autodesk Fusion 2025 Tutorial: User Interface
Atif Razi
 

A Counterexample to the Forward Recursion in Fuzzy Critical Path Analysis Under Discrete Fuzzy Sets

  • 1. International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016 DOI : 10.5121/ijfls.2016.6204 53 A COUNTEREXAMPLE TO THE FORWARD RECURSION IN FUZZY CRITICAL PATH ANALYSIS UNDER DISCRETE FUZZY SETS Matthew J. Liberatore1 1 Department of Management and Operations, Villanova School of Business, Villanova University, Villanova, PA 19085 ABSTRACT Fuzzy logic is an alternate approach for quantifying uncertainty relating to activity duration. The fuzzy version of the backward recursion has been shown to produce results that incorrectly amplify the level of uncertainty. However, the fuzzy version of the forward recursion has been widely proposed as an approach for determining the fuzzy set of critical path lengths. In this paper, the direct application of the extension principle leads to a proposition that must be satisfied in fuzzy critical path analysis. Using a counterexample it is demonstrated that the fuzzy forward recursion when discrete fuzzy sets are used to represent activity durations produces results that are not consistent with the theory presented. The problem is shown to be the application of the fuzzy maximum. Several methods presented in the literature are described and shown to provide results that are consistent with the extension principle. KEYWORDS critical path analysis, discrete fuzzy sets, forward recursion, counterexample, project scheduling 1. INTRODUCTION CPM or the critical path method [11] has been successfully applied to plan and control projects that are organized as a set of inter-related activities. PERT or Program Evaluation and Review Technique [16] and Monte Carlo simulation apply probability analysis to address situations where there is uncertainty related to activity duration. PERT models uncertainty by collecting optimistic, most likely and pessimistic duration estimates of all activities and makes certain assumptions about the underlying probability distributions. Since the basic version of PERT tends to underestimate the expected minimum project duration [15]. Monte Carlo simulation is often preferred in practice when activity durations are uncertain. However, the information required to estimate probabilities related to activity duration may not always be known. Fuzzy logic is an alternative approach for measuring uncertainty related to activity duration. Fuzzy logic measures imprecision or vagueness in estimation, and may be preferred to probability theory in those situations where past data concerning activity duration is either unavailable or not relevant, the definition of the activity itself is somewhat unclear, or the
  • 2. International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016 54 notion of the activity’s completion is vague. Many authors including Chanas and colleagues have investigated the situation when activity duration can be described by fuzzy numbers [1], [2], [3], 5], [6], [7]. The dominant approach presented in the fuzzy critical path analysis literature is the fuzzy extension of the forward and backward recursions taken in the project network. This approach computes the earliest and latest start and finish times and slack, where the maximum, minimum, addition, and subtraction operators are replaced by their fuzzy counterparts. The application of the forward recursion with fuzzy activity times was first demonstrated in [3]. In a review of the fuzzy critical path analysis literature two approaches are described for applying the forward recursion [4]. They also indicate that the application of the backward recursion would cause a considerable increase in the range of uncertainty in the start and finish times that are calculated. These authors present a modification of the backward recursion that has been proposed to eliminate this disadvantage [12]. Some authors directly apply the backward recursion, while other authors have proposed different approaches for modifying the backward pass when the activity times are fuzzy [18], [19], [20], [22]. The backward recursion was found not to compute the sets of the possible values of the latest starting times and floats of activities [22]. In a stream of research that uses the joint possibility distribution of activity durations, several authors [8], [9] have conducted preliminary work for computing fuzzy latest starting times and fuzzy floats, especially for series-parallel graphs. Polynomial algorithms for determining the intervals of the latest starting times in the general project network are presented in [22]. Unlike the fuzzy backward recursion, the use of the fuzzy forward recursion is generally accepted in the literature as providing correct results. As mentioned by several authors [3], [10], [18], [19], the forward recursion is correct on problems involving fuzzy intervals. The purpose of this paper is to prove that the fuzzy forward recursion when discrete fuzzy sets are used to represent activity durations provides results that are not consistent with the direct application of the extension principle to the critical path problem. In section 2, we present some background on fuzzy sets and the supporting concepts needed in the remainder of the paper. In section 3 we provide some brief background on project network analysis under the assumption that activity durations are certain. Section 4 presents an important result for fuzzy critical path analysis based on the extension principle. In section 5 the counterexample to the application of the fuzzy forward recursion is presented and the reason the results are not consistent with the extension principle is shown. Section 6 discusses two proposed approaches from the literature that present results consistent with the extension principle. Conclusions are offered in section 7. 2. FUZZY SETS Following [17] we give the following definitions of a fuzzy set, fuzzy quantity and the support set: Definition 1. A fuzzy set M is a subset of the universe U that is characterized by a membership function Mµ : U→[0,1] such that:
  • 3. International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016 55 ( )M xµ = 0, if x certainly is not a member of M, ( )M xµ = 1, if x certainly is a member of M, ( ) (0,1)M xµ ∈ , if it is uncertain whether x is a member of M, where ( )M xµ represents the degree to which x is a member of M. Now assume that activity duration is uncertain due to vagueness or imprecision and is a fuzzy quantity defined as follows: Definition 2. A fuzzy quantity M is a fuzzy subset of with membership function [ ]: 0,1Mµ → such that sup( ( ) : ) 1M x xµ ∈ = (1a) ( ) 1 2 1 2 1 2 , , : , , ( ) 0 M M M M M M M x x x x x x x x xµ ∃ ∈ < ∀ ∈ ∉ ⇒ = (1b) Definition 3. The support set of Mµ is defined as { }| ( ) 0M MS x xµ= ∈ > . This definition can include discrete as well as continuous fuzzy sets, such as those that are triangular or trapezoidal in shape. If the support set MS is finite, condition (1a) above can be replaced with 0 0: ( ) 1Mx xµ∃ ∈ = . To simplify the presentation, we will assume this condition hereafter. Condition (1b) implies that the support set is bounded. We will also assume that the support set is discrete. Let iS be the support set of ia , where , , 1,2,...,i k i it S k n∈ = . That is, ia has in possible non-zero discrete durations ,i kt in its support set iS . As an example of a fuzzy activity duration, the vague statement that the duration of activity ia is “about six weeks” might be represented by the following fuzzy quantity ~ it whose membership function will be denoted as: (6) .7, (7) 1.0, (8) .8, ( ) 0i i i i itµ µ µ µ= = = = , otherwise. We can also denote this membership function as 6/0.7, 7/1.0, 8/0.8. We also need to define fuzzy addition and the fuzzy maximum of fuzzy quantities. Let 1M and 2M be fuzzy quantities with membership functions 1Mµ and 2Mµ , respectively. Following [17] and as a direct application of the extension principle: Definition 4. Fuzzy Addition: The membership function for the fuzzy quantity 21 MM ⊕ is defined as: )(21 zMM ⊕µ = Max Min { }1 2 ( ), ( )M Mx yµ µ (2)
  • 4. International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016 56 z x y= + Definition 5. Fuzzy Maximum: The membership function for the fuzzy quantity max (M1, M2) is defined as: 1 2max( , ) ( )M M zµ = Max Min { }1 2 ( ), ( )M Mx yµ µ (3) max( , )z x y= One final definition is needed: Definition 6: A configuration Ω is defined as a precise instantiation of the duration of all ia Aε . In the next section we provide the necessary background on project network analysis. 3. BACKGROUND ON PROJECT NETWORKS AND THE CRITICAL PATH Let { }1 2,, ..., NA a a a= be the set of project activities. Let iB , i=1,2,…,N, iB A⊂ , be defined so that the elements of iB are the immediate predecessors of ia . We let { }1 2, ,..., NB B B B= be the set of predecessor sets. Cycles of activities within the project network are not allowed. We assume that 1a is the only element of A such that 1B = ∅. We also assume Na is the only element of A such that .N ia B i N∉ ∀ ≠ If the project network does not have unique start and finish activities, we add dummy activities (which have zero duration) for this purpose. Taken together A and B define the network structure or graph G of a project. We initially assume that it ∈ , 0it ≥ , is the certain duration for ia , where { }1 2, ,..., NT t t t= . A path p from start to finish is a finite sequence of activities { }1 2 , ,..., sr r ra a a where 1 , 1,2,..., 1k kr ra B k s+ ∈ = − , and 1 1ra a= and sr na a= . The length of the longest path from the start activity to the finish activity is the minimum project completion time. This path is called the critical path, the activities along it are called critical path activities, and the length of the path is denoted as CPL . Given G for each unique set of values T we can compute CPL . Therefore, there is a function f(T|G): ...× × × → that maps T to CPL , or CPL = f(T|G). 4. FUZZY CRITICAL PATH ANALYSIS Proposition 1: Fuzzy Critical Path Membership Function The membership function for the fuzzy set of critical path lengths can be determined as:
  • 5. International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016 57 ( )CP CPLµ = Max Min { }( )i itµ (4) 1 2, ,..., Nt t t { }1,2,...,i N∈ 1 2( , ,..., | )N CPf t t t G L= where ( )CP CPLµ is the membership function for the length of the critical path over the fuzzy subset CP in ; and for a graph G and activity durations 1 2, ,..., Nt t t , 1 2( , ,..., | )Nf t t t G determines the length of the critical path. Proof: direct application of the extension principle of fuzzy logic [21] using maximum and minimum for the disjunction and conjunction operators, respectively. Because Proposition 1 represents the direct generalization of critical path analysis from the crisp to the fuzzy domain, any proposed fuzzy critical path analysis approach should provide results that are consistent with it. One approach for implementing Proposition 1 requires defining all possible configurations, determining the belief of each configuration as the minimum of the beliefs associated with all activity durations included in this configuration, and then determining the maximum belief of all configurations leading to each possible critical path length. The results form the fuzzy set of critical path lengths. 5. COUNTER EXAMPLE TO THE FUZZY FORWARD RECURSION In standard CPM the earliest start (ESi) and earliest finish (EFi) of an activity are defined as: ESi = max EFj (5) ij B∈ where we set ES0 = 0, and EFi = ESi + it (6) As defined in section 3 activity N does not have any successors, and so EFN is the length of the critical path. Assuming it% is a fuzzy quantity representing the duration of ia , the fuzzy earliest start iES and fuzzy earliest finish iEF are defined as follows: maxi jES EF= (7) ij B∈
  • 6. International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016 58 i i iEF ES t= ⊕% (8) where max and ⊕ represent the extended fuzzy maximum and fuzzy addition, respectively, as given in definitions 4 and 5. Proposition 2: The fuzzy forward recursion does not always yield membership functions for the fuzzy set of critical path lengths that are consistent with Proposition 1. Proof: By counterexample using the data from a simple series – parallel graph (these graphs are defined in [8] as shown in Figure 1. In this example there 2*3*3*1 = 18 configurations as shown in Table 1. For each configuration, we determine the lengths of all paths, identify the critical path, and following Proposition 1 determine the configuration belief as the minimum of the beliefs of the possible activity durations. We combine the configurations by taking the maximum of the beliefs over all configurations having the same critical path length. From Table 1 the fuzzy set of critical path lengths is shown to be: ( )CP CPLµ = 6/0.1, 7/0.2, 8/0.5, 9/0.2, 10/0.5, 11/0.1, 12/1 (9) The fuzzy forward recursion is applied using equations (5) and (6), with fuzzy addition and fuzzy maximum as defined in equations (2) and (3), respectively. The results are as follows: 1ES = 0/1 (10) 1EF = 0/1 ⊕ (3/0.5, 5/1) = 3/0.5, 5/1 (11) 2ES = 1EF = 3/0.5, 5/1 (12) 2EF = (3/0.5, 5/1) ⊕ (3/0.2, 5/0.5, 7/1) = 6/0.2, 8/0.5, 10/0.5, 12/1 (13) 3ES = 1EF = 3/0.5, 5/1 (14) 3EF = (3/0.5, 5/1) ⊕ (2/0.1, 4/1, 6/0.1) = 5/0.1, 7/0.5, 9/1, 11/0.1 (15) 4ES = max { 2EF , 3EF } (16) = max {(6/0.2, 8/0.5, 10/0.5, 12/1), (5/0.1, 7/0.5, 9/1, 11/0.1)} = 6/0.1, 7/0.2, 8/0.5, 9/0.5, 10/0.5, 11/0.1, 12/1 4EF = (6/0.1, 7/0.2, 8/0.5, 9/0.5, 10/0.5, 11/0.1, 12/1) ⊕ 0/1 (17) = 6/0.1, 7/0.2, 8/0.5, 9/0.5, 10/0.5, 11/0.1, 12/1 where 4EF is by definition ( )CP CPLµ , the fuzzy set of critical path lengths.
  • 7. International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016 59 A comparison of equations (9) and (17) show that the range of possible critical path lengths is the same, but that the belief of the possible critical path length of 9 is 0.2 in equation (9) and 0.5 in equation (17). This difference proves the assertion. Discussion: The forward algorithm is generally regarded as providing correct results in the literature, with no distinction made for activity durations represented as discrete fuzzy sets. The difference in the belief for the possible critical path length of 9 from Example 1 results from incorrect comparisons made in the computation of the fuzzy maximum of the earliest finishes. Specifically, the fuzzy maximum incorrectly compares earliest finish values that are based on activity durations from different configurations. These configurations differ in terms of the possible values of the activity that is the immediate predecessor of those activities whose earliest finishes are being compared. For example, in equation (16) the possible time 8/0.5 from 2EF is compared with the possible time 9/1 from 3EF to yield 9/0.5. Folding back, in equation (13) the possible duration 8/0.5 results from the addition of 3/0.5 from 1EF and 5/0.5 from the possible duration of 2a . Since the 1ES is 0, 3/0.5 is the possible duration of 1a . In equation (15) the possible duration 9/1 results from the addition of 5/1 from 1EF and 4/1 from the possible duration of 3a . Since the 1ES is 0, 5/1 is the possible duration of 1a . That is, different possible durations of 1a are used to obtain the possible time 8/0.5 from 2EF and the possible time 9/1 from 3EF . Thus, the fuzzy maximum incorrectly compares earliest finishes that are based on activity durations from different configurations. In the example above, if the possible duration of 1a were 3/0.2 instead of 3/0.5, then the fuzzy forward recursion would have produced the correct result, simply because of the specific value of a belief. However, since the fuzzy maximum is used repeatedly in the application of the fuzzy forward recursion, errors are likely to occur in many, if not most, problems. 6.PROPOSED CRITICAL PATH METHODS THAT ARE CONSISTENT WITH THE EXTENSION PRINCIPLE This author has proposed several alternative approaches for computing the fuzzy set of critical path lengths that are consistent with the extension principle and Proposition 2. The first approach [13] is based on the idea that rather than enumerate all possible configurations, generate and then analyze a small number of configurations to achieve convergence to the membership function of the fuzzy set of critical path lengths. This method uses pseudo-random numbers to select possible durations for each activity to form configurations. Either the standard forward pass or path enumeration can be applied to determine the critical path length of a configuration. Following Proposition 1, the belief associated with the possible critical path length of a given configuration is the minimum of the beliefs of the possible activity durations in the configuration. Since several configurations may lead to the same possible critical path length, again following Proposition 1 and the extension principle, the belief of a possible critical path length is the maximum of the beliefs associated with all possible critical path lengths of the same duration. Additional
  • 8. International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016 60 configurations are analyzed until the percentage change in AREA (sum of the products of all possible critical path lengths and their beliefs) is less than some tolerance. The proposed method is evaluated using a series of test problems from the literature. The second approach [14] begins by using a standard forward-backward pass algorithm to compute the minimum possible critical path length, using the smallest possible duration for each activity. A similar approach determines the maximum possible critical path length. Following Proposition 1 a mathematical programming problem is formulated, whose objective is to determine the belief associated with a possible critical path length. This mathematical program is run for all possible critical path lengths, ranging between the possible minimum and maximum lengths. In this way, the membership function for the fuzzy set of critical path lengths is constructed. The proposed method is evaluated using a series of test problems from the literature. 7. CONCLUSIONS In this paper, the direct application of the extension principle leads to a proposition that must be satisfied in fuzzy critical path analysis. Using a counterexample where discrete fuzzy sets are used to represent activity durations, it is demonstrated that the fuzzy forward recursion produces results that are not consistent with the theory presented. The problem is shown to be the application of the fuzzy maximum, since it compares earliest finishes that are based on activity durations from different configurations. Several methods offered in the literature that provide results consistent with the extension principle are described. The development of more efficient algorithms to compute the fuzzy set of critical path lengths is an area of further research. Figure 1. Example network with fuzzy activity durations
  • 9. International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016 61 Table 1: Applying proposition 1 to the example Activity 1 Activity 2 Activity 3 P 1 - 2 - 4 P 1 - 3 - 4 Critical Path CP fuzzy set Duration Belief Duration Belief Duration Belief Duration Duration Duration Belief Duration Belief 3 0.5 3 0.2 2 0.1 6 5 6 0.1 6 0.1 3 0.5 3 0.2 4 1 6 7 7 0.2 7 0.2 3 0.5 3 0.2 6 0.1 6 9 9 0.1 8 0.5 3 0.5 5 0.5 2 0.1 8 5 8 0.1 9 0.2 3 0.5 5 0.5 4 1 8 7 8 0.5 10 0.5 3 0.5 5 0.5 6 0.1 8 9 9 0.1 11 0.1 3 0.5 7 1 2 0.1 10 5 10 0.1 12 1 3 0.5 7 1 4 1 10 7 10 0.5 3 0.5 7 1 6 0.1 10 9 10 0.1 5 1 3 0.2 2 0.1 8 7 8 0.1 5 1 3 0.2 4 1 8 9 9 0.2 5 1 3 0.2 6 0.1 8 11 11 0.1 5 1 5 0.5 2 0.1 10 7 10 0.1 5 1 5 0.5 4 1 10 9 10 0.5 5 1 5 0.5 6 0.1 10 11 11 0.1 5 1 7 1 2 0.1 12 7 12 0.1 5 1 7 1 4 1 12 9 12 1 5 1 7 1 6 0.1 12 11 12 0.1 *activity 4 is a dummy whose duration is certainly 0 REFERENCES [1] Chanas, S. (1982) “Fuzzy sets in few classical operational research problems” in Gupta M. & Sanches, E. (eds.), Approximate Reasoning in Decision Analysis, North-Holland Publishing Company, pp. 351-361. [2] Chanas, S., Dubois, D. & Zielinksi, P. (2002) “On the sure criticality of tasks in activity networks with imprecise durations”, IEEE Transactions on Systems, Man, and Cybernetics – Part B: Cybernetics, Vol. 32, pp. 393-407. [3] Chanas, S. & Kamburowski, J. (1981) “The use of fuzzy variables in PERT”, Fuzzy Sets and Systems, Vol. 1, pp. 11 – 19. [4] Chanas, S. & Kuchta, D. (1998) “Discrete fuzzy optimization”, Chapter 8 in Slowinski, R. (ed.), Fuzzy sets in Decision Analysis, Operations Research and Statistics, Kluwer Academic Publishers, Boston, pp. 249-280. [5] Chanas, S. & Zielinski, P. (2001) “Critical path analysis in the network with fuzzy activity times”, Fuzzy Sets and Systems, Vol. 122, pp. 195-204. [6] Chanas, S. & Zielinski, P. (2002) “The computational complexity of the criticality problems in a network with interval activity times”, European Journal of Operational Research, Vol. 136, pp. 541 – 550. [7] Chanas, S. & Zielinski, P. (2003) “On the hardness of evaluating criticality of activities in a planar network with duration intervals”, Operations Research Letters, Vol. 31, pp. 53 – 59. [8] Dubois, D., Fargier, H. & Galvagnon, V. (2003) “On the latest starting times and floats in activity networks with ill-known durations”, European Journal of Operational Research, Vol. 147, pp. 266- 280. [9] Fargier, H., Galvagnon, V. & Dubois, D. (2000) “Fuzzy PERT in series-parallel graphs”, in Ninth IEEE International Conference on Fuzzy Systems, San Antonio, TX, pp. 717-722.
  • 10. International Journal of Fuzzy Logic Systems (IJFLS) Vol.6, No.2,April 2016 62 [10] Hapke, M., & Slowinski, R. (1996) “Fuzzy priority heuristics for project scheduling”, Fuzzy Sets and Systems, Vol. 83, pp. 291-299. [11] Kelley, J. (1961) “Critical path planning and scheduling -- mathematical basis”, Operations Research, Vol. 9, pp. 296-320. [12] Kamburowski, J. (1983) “Fuzzy activity duration times in critical path analysis”, International Symposium on Project Management, New Delhi, pp. 194-199. [13] Liberatore, M. (2007) “A latin hypercube sampling approach for fuzzy critical path analysis”, International Journal of Operations and Quantitative Management, Vol. 13, No. 4, pp. 235 – 250. [14] Liberatore, M. (2008) ”Critical path analysis with fuzzy activity times”, IEEE Transactions on Engineering Management, Vol. 55, No. 2, pp. 329 - 337. [15] Lootsma, F. A. (1989) “Stochastic and fuzzy PERT”, European Journal of Operational Research, Vol. 43, pp. 174-183. [16] Malcolm, D., Rosenbloom, J., Clark, C. & and Fazar, W. (1959) “Application of a technique for research and development project evaluation”, Operations Research, Vol. 7, pp. 646-669. [17] Mares, M. (1994) Computation Over Fuzzy Quantities, CRC Press, Boca Raton. [18] Nasution, S. (1994) “Fuzzy critical path method”, IEEE Transactions on Systems, Man, and Cybernetics, Vol. 24, pp. 48-57. [19] Rommelfanger, H. (1994) “Network analysis and information flow in fuzzy environment”, Fuzzy Sets and Systems, Vol. 67, pp. 119-128. [20] Slyeptsov, A. & Tyschchuk, T. (2003) “A method of computation of characteristics of operations in a problem of fuzzy network planning and management”, Cybernetics and Systems Analysis, Vol. 39, pp. 367 – 378. [21] Zadeh, L. (1975) “Calculus of fuzzy restrictions”, in Zadeh, L., Fu, K., Tanaka, K. & Shimara, J. (eds.), Fuzzy Sets and Their Application to Cognitive and Decision Processes, Academic Process, pp. 1-39. [22] Zielinski, P. (2005) “On computing the latest starting times and floats of activities in a network with imprecise durations”, Fuzzy Sets and Systems, Vol. 150, pp. 53 – 76.
  翻译: